Calculator — Budget & Planning

Renovation Budget Calculator

Split a renovation budget across labor, materials, permits, design and contingency — with the guideline percentages and a bar breakdown.

Inputs

$
%
%
%
%
%

Results

Adjust the inputs to see your result.

About this calculator

A renovation budget is five numbers, not one: labor about 40%, materials about 35%, permits and fees about 5%, design about 5%, and a 10–20% contingency for what nobody can see yet. This calculator splits your total across those lines, shows each as an amount and a share of the budget, and lets you override any guideline share.

What this number means

A renovation budget is not one number, it is five: labor, materials, permits, design and the contingency that covers what nobody can see yet. The guideline split used here — labor about 40%, materials about 35%, permits and fees about 5%, design about 5%, contingency 10–20% — matches how real remodel budgets land on mid-range projects. Labor leads because a remodel is mostly skilled hours, not stuff.

The contingency is the line most budgets get wrong. A 15% reserve on a $50,000 project is $7,500, and it is not spare money: it is the rotten subfloor, the wiring that is not up to code, the pipe in the wrong place. If the contingency is never spent, it is the only line that comes back to you — every other line is committed the moment work starts.

The formula

  • Contingency = Total budget × contingency %
  • Remaining = Total budget − Contingency
  • Labor = Remaining × (labor % ÷ sum of the four category %s)
  • Materials, permits, design = same, with their own %
  • Category amounts always add up to the total budget — editing a % re-weights that category within the remaining pot

Worked example

A $50,000 kitchen remodel with a 15% contingency and the guideline split.

  • Contingency: $50,000 × 15% = $7,500
  • Remaining to allocate: $50,000 − $7,500 = $42,500
  • Labor: $42,500 × 40 ÷ 85 = $20,000
  • Materials: $42,500 × 35 ÷ 85 = $17,500
  • Permits & fees: $42,500 × 5 ÷ 85 = $2,500
  • Design: $42,500 × 5 ÷ 85 = $2,500
  • Total allocated: $7,500 + $20,000 + $17,500 + $2,500 + $2,500 = $50,000

Assumptions and limitations

  • Guideline percentages are planning figures for a typical mid-range remodel, not quotes. Labor-heavy work (structural, plumbing moves) pushes labor above 40%; material-heavy work (stone, custom cabinetry) pushes materials above 35%.
  • Amounts are pre-tax planning figures. Add your local sales tax to the materials line — rates vary by state and some states tax labor too.
  • Permit costs vary widely by city and project scope; 5% covers most residential permits but a structural project in a high-fee city can exceed it.
  • Design at 5% assumes a designer or architect is involved. A DIY design is 0% — set the share to 0 and the other categories absorb it.
  • The calculator assumes the contingency is held inside the total budget. If your contingency sits on top of the budget instead, enter budget + contingency as the total.

Frequently asked questions